MPS


Developing a MPS


The objectives in developing an MPS are as follows:
- To maintain the desired level of customer service by maintaining finishedgoods inventory levels or by scheduling to meet customer delivery requirements;
- To make the best use of material, labor and equipment;
- To maintain inventory investment at the required levels.

To reach this objectives, there are 3 steps in preparing a MPA:

4. Master Production Schedule

The MPS (Master Production Schedule) define precisely the required quantity per period for each finished product to sell. The bucket is usually the week and the time horizon up to 3-6 months or a least twice the longest product leadtime.