  • Books for BSCM   6 years 39 weeks ago

    i am started studying from basics of supply chain management reprints and i am kind of lost!!

    i am not sure if i am doing the right thing, my exam is in one month!

  • Reschedule in   6 years 39 weeks ago

    Due Date - The date on which the item is going to be made available by the system
    Need Date - The date on which the item is required as per the demand (customer order or Work Order/Job)
     

  • Books for BSCM   6 years 39 weeks ago

    You don’t need any study guide for the first paper. ..Just read Tony Arnold …that is more than sufficient
    Just to give you an idea about participant workshop and study notes

    participant workshop usually contains all the areas covered in exam
    the guide is usually meant to be used in a class room…not for self study…

    I have not attended any class room but still found these guide books quite worthy (for DSP & ECO)..

    Study notes are written more like books and quite interesting to read but they don’t cover all the areas asked in the exam.

     

  • Reschedule in   6 years 39 weeks ago

    Thanks !!!

    But my question is what is the difference between due date and need date

  • Reschedule in   6 years 39 weeks ago

    If the due date of an order is later than the need date then system 'll put a message to reschedule in the order.

    So answer is B

  • critical ratios   6 years 41 weeks ago

    The correct ans is B i.e. C D B & A

  • how to solve this   6 years 41 weeks ago

    Let SP = 100
    Total Cost = 90
    Mfg Cost = 60
    Var Cost = 30

    Now Mgf cost is changed to 50
    So Total cost = 80

    Profit = 20

    i.e. Profit is increased by 100%

  • results   6 years 42 weeks ago

    I cleared first 2 papers BSCM & MPR with 310 + scores